Al Zahra Private Palace
Multiple Phase Renovation
General Contractor.
Phase 1:
- Refitting & re-routing of the water supply system whilst maintaining running water to all Bathrooms & Kitchens.
- Restoration of Marble & gypsum works.
Phase 2:
- Total renovation of Master Suite.
Phase 3:
- Total Restoration of South Wing.
Phase 1: 2 Months.
Phase 2: 2 Months.
Phase 3: 1 Month.
Phase 1: JAN 2017.
Phase 2: MAY 2018.
Phase 3: MAR 2020.